Beginning this winter, CenterPoint Energy (formerly Vectren) will perform gas main upgrades in downtown Troy. Dates have been moved up from previous estimates, and construction is scheduled to begin on February 2. The project is slated for completion by early April.
To assist downtown residents and businesses in planning for parking disruptions, Ritter Construction, the contractor for the project, has provided the following tentative schedule. As crews move through each area, parking may be limited and sidewalk interruptions may occur.
February 18: Northeast quadrant will be closed.
February 21: Southwest quadrant will be closed.
February 21-25 and February 28: No parking on west side of South Market Street.
February 22 and 23: Southeast quadrant will be closed.
February 24 and 25: Northeast quadrant will be closed.
March 1 and 2: No parking on east side of South Market Street.
March 7 to March 11: Work will take place on W. Main Street.
March 14 to March 18: Work will take place on S. Market Street.
March 21 to March 25: Work will take place on E. Main Street.
March 28 to April 4: Additional work on N. Market and Water Street will take place as needed.
The City is working closely with CenterPoint to limit disruption to downtown residents and businesses. A representative from Ritter Construction will continue to correspond with businesses and residents to provide more information.
For more information about CenterPoint’s gas system and upgrades, click here.