West Main Street Updates

Posted on: August 11, 2023

West Main Update - 8/11/2023

West Main Updates from Prime Engineering:

This week, crews milled existing asphalt and placed new intermediate asphalt west of the West Main and Ridge Avenue intersection. Thanks to all who were patient with the lane shifts and periodic closures of side streets and intersections, allowing crews to work and asphalt to cool. It’s truly appreciated!


Week of 8/14 – Crews will move the milling/paving operation to the area of Monroe to Plum, and West Main will be closed from Monroe to Plum this week. No-parking signs will be posted, and areas of Oxford, Short, and Plum Streets may also have areas marked for no-parking.


Once paving is complete for the intermediate asphalt, temporary striping will be applied, and the street will be re-opened.


Motorists will be driving on temporary asphalt until the area of construction is completed between Elm and Adams Streets, as construction on a boulevard-style central median continues. The final result will be an island that includes landscaping and lighting. While this island is being constructed, motorists will be traveling in the curb lanes in each direction.


Surface course asphalt will be placed when all work is completed so that motorists can enjoy the new and improved rideability of West Main Street. As always, we thank you for your patience and understanding!


As always, please contact us for more information at MainStImprovements@primeeng.com. Upcoming road closures can be viewed here.

Facebook Twitter Email

Other News in West Main Street Updates

West Main Update - 11/9/2023

Posted on: November 9, 2023

West Main Update - 10/24/2023

Posted on: October 24, 2023

West Main Update - 10/6/2023

Posted on: October 6, 2023

West Main Update - 10/2/2023

Posted on: October 2, 2023

West Main Update - 9/25/2023

Posted on: September 25, 2023

West Main Construction Update -- 9/14

Posted on: September 14, 2023
whatsupintroy-default

West Main Update - 9/1/2023

Posted on: September 1, 2023

West Main Update - 8/18

Posted on: August 18, 2023

West Main Update - 7/31/2023

Posted on: July 31, 2023

West Main Update - 7/21/2023

Posted on: July 21, 2023

West Main Update - 7/10/2023

Posted on: July 10, 2023

West Main Update - June 23, 2023

Posted on: June 23, 2023

West Main Update - 6/9/2023

Posted on: June 9, 2023

West Main Updates 5-26-2023

Posted on: May 26, 2023

West Main Update - 5/11/2023

Posted on: May 11, 2023

West Main Update for 4/21

Posted on: April 21, 2023

West Main Update - 4/6/2023

Posted on: April 6, 2023

West Main Updates for 3/27

Posted on: March 27, 2023

West Main Update - 3/17/2023

Posted on: March 17, 2023
conduit

West Main Update - 3/7/2023

Posted on: March 7, 2023

West Main Update - 2/13/2023

Posted on: February 13, 2023

West Main Update - 1/24/2023

Posted on: January 24, 2023

West Main Updates 1/6/2023

Posted on: January 6, 2023

West Main Update - 12/20/2022

Posted on: December 20, 2022

West Main Update - 12/13/2022

Posted on: December 13, 2022
whatsupintroy-default

West Main Update - 11/21/2022

Posted on: December 13, 2022

West Main Updates - 11/14/2022

Posted on: November 14, 2022

West Main Updates - 11/7/2022

Posted on: November 7, 2022

West Main Updates - 10/24/2022

Posted on: October 24, 2022

West Main Updates 10/17/2022

Posted on: October 14, 2022

West Main Update 10/10

Posted on: October 12, 2022

West Main Updates 9/30

Posted on: September 30, 2022

West Main Update 9/23/2022

Posted on: September 23, 2022

West Main Update 9/1/2022

Posted on: September 1, 2022

West Main Update 8/26

Posted on: August 26, 2022