West Main Update - 10/2/2023

Last week had some weather challenges, but crews managed to complete several tasks between rain showers:

  • Surface course asphalt was completed between the railroad tracks and Ridge Avenue, the intersection of Plum and West Main, and portions of pavement at Short Street.
  • Temporary striping was placed Friday, as final paving is yet to come between Plum and the railroad tracks. 
  • Crews continued adjusting manholes and valves throughout the project.


This week:  

  • Permanent signage will be installed.
  • Concrete crews will continue to work near downtown, around the West Main and Cherry intersection. 
  • Contractor and gas company personnel will continue to locate and adjust all manholes and valves in the roadway for final paving.
  • Paving crews will be in to prep entrances to West Main for final paving between Plum and the railroad tracks. Final paving has been tentatively scheduled for the week of October 9th.
  • Permanent pavement markings will follow paving.


As always, motorists should use caution, and if possible, take alternate routes. We appreciate your continued patience.

Facebook Twitter Email

Other News in West Main Street Updates

West Main Update - 11/9/2023

Posted on: November 9, 2023

West Main Update - 10/24/2023

Posted on: October 24, 2023

West Main Update - 10/6/2023

Posted on: October 6, 2023

West Main Update - 9/25/2023

Posted on: September 25, 2023

West Main Construction Update -- 9/14

Posted on: September 14, 2023
whatsupintroy-default

West Main Update - 9/1/2023

Posted on: September 1, 2023

West Main Update - 8/18

Posted on: August 18, 2023

West Main Update - 8/11/2023

Posted on: August 11, 2023

West Main Update - 7/31/2023

Posted on: July 31, 2023

West Main Update - 7/21/2023

Posted on: July 21, 2023

West Main Update - 7/10/2023

Posted on: July 10, 2023

West Main Update - June 23, 2023

Posted on: June 23, 2023

West Main Update - 6/9/2023

Posted on: June 9, 2023

West Main Updates 5-26-2023

Posted on: May 26, 2023

West Main Update - 5/11/2023

Posted on: May 11, 2023

West Main Update for 4/21

Posted on: April 21, 2023

West Main Update - 4/6/2023

Posted on: April 6, 2023

West Main Updates for 3/27

Posted on: March 27, 2023

West Main Update - 3/17/2023

Posted on: March 17, 2023
conduit

West Main Update - 3/7/2023

Posted on: March 7, 2023

West Main Update - 2/13/2023

Posted on: February 13, 2023

West Main Update - 1/24/2023

Posted on: January 24, 2023

West Main Updates 1/6/2023

Posted on: January 6, 2023

West Main Update - 12/20/2022

Posted on: December 20, 2022

West Main Update - 12/13/2022

Posted on: December 13, 2022
whatsupintroy-default

West Main Update - 11/21/2022

Posted on: December 13, 2022

West Main Updates - 11/14/2022

Posted on: November 14, 2022

West Main Updates - 11/7/2022

Posted on: November 7, 2022

West Main Updates - 10/24/2022

Posted on: October 24, 2022

West Main Updates 10/17/2022

Posted on: October 14, 2022

West Main Update 10/10

Posted on: October 12, 2022

West Main Updates 9/30

Posted on: September 30, 2022

West Main Update 9/23/2022

Posted on: September 23, 2022

West Main Update 9/1/2022

Posted on: September 1, 2022

West Main Update 8/26

Posted on: August 26, 2022